What is the maximum time-box for Sprint Planning?

Prepare for the Professional Scrum Master I Test. Tackle multiple choice questions with hints and explanations. Get ready to ace your exam!

The maximum time-box for Sprint Planning is indeed 8 hours for a one-month Sprint. This duration is significant because it allows the Scrum Team, including the Product Owner and Development Team, ample time to discuss and refine the work that they will commit to in the upcoming Sprint. During this meeting, the team collaborates to understand the goals of the Sprint, the backlog items chosen, and the tasks required to achieve the Sprint Goal.

It's important to note that this time-box is flexible; for shorter Sprints, such as those lasting two weeks, the time-box for Sprint Planning can be reduced appropriately. The 8-hour guideline serves as a standard for longer Sprints, ensuring that the team has enough time to engage in meaningful dialogue, ask questions, clarify details, and achieve a shared understanding of the work ahead. This collaborative approach fosters transparency and alignment within the team, ultimately enhancing their productivity and focus during the Sprint.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy