What is the main goal of the Sprint Review?

Prepare for the Professional Scrum Master I Test. Tackle multiple choice questions with hints and explanations. Get ready to ace your exam!

The main goal of the Sprint Review is to obtain stakeholder feedback. This event occurs at the end of a Sprint and provides an opportunity for the Scrum Team to showcase their work to stakeholders and other interested parties. The team demonstrates the increment of product that has been developed during the Sprint, which allows stakeholders to see the current state of the project.

This feedback is crucial for several reasons. It ensures that the development work aligns with stakeholder expectations and needs, enabling the team to understand what is working and what may need adjustment. Additionally, it fosters collaboration and transparency between the Scrum Team and stakeholders, reinforcing the iterative nature of Scrum where the product evolves based on feedback.

While it may be tempting to think of the Sprint Review as a time to finalize the project or prepare for the next Sprint, those are not its primary goals. The focus during this event is on gathering feedback and adapting the product based on that input, which ultimately guides the next steps for the team.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy