What is produced as an output of the Sprint Review?

Prepare for the Professional Scrum Master I Test. Tackle multiple choice questions with hints and explanations. Get ready to ace your exam!

The output of the Sprint Review primarily includes feedback from stakeholders and potentially shippable product increments. During the Sprint Review, the Scrum Team presents the work completed during the Sprint, which is assessed against the Sprint Goal. This presentation demonstrates the increment of work that is potentially shippable, meaning it meets the Definition of Done and can be released if deemed valuable.

Feedback from stakeholders is crucial at this stage as it helps refine the product vision and priorities. Stakeholders provide insights and suggestions based on what has been delivered, which can inform subsequent Sprints and help the Product Owner adjust the Product Backlog. The collaborative nature of the Sprint Review fosters an environment where the Scrum Team can discuss past performance, current deliverables, and future direction together with those who have a vested interest in the product's success.

In contrast, project schedules and timelines are typically determined outside of the Sprint Review process. Team performance metrics may be collected and analyzed, but they are not a direct output from the Sprint Review itself. As for new tasks for the Product Backlog, while they may arise as a result of discussions during the review, they are not formalized outcomes but rather influenced by stakeholder feedback and team insights.

Thus, the correct answer centers on the dual significance of