What does the Sprint Backlog consist of?

Prepare for the Professional Scrum Master I Test. Tackle multiple choice questions with hints and explanations. Get ready to ace your exam!

The Sprint Backlog is a specific subset of the Product Backlog that consists of the items selected for the current Sprint as well as the plan for delivering those items. This means that it includes not only the selected Product Backlog items that the team has committed to complete during the Sprint but also the detailed tasks that the team needs to carry out in order to achieve the Sprint Goal.

By having both the selected items and the development plan in the Sprint Backlog, the Scrum Team maintains a clear focus on what needs to be accomplished in that Sprint, allowing for effective tracking and adjustment throughout the Sprint. This dual nature of the Sprint Backlog fosters collaboration and helps ensure that the team remains aligned with their goals.

In contrast, other options do not encompass the full definition of the Sprint Backlog. For example, merely including all remaining Product Backlog items does not capture the essence of a Sprint, which is about committing to a specific set of items for a defined timeframe. Additionally, referencing previously completed Product Backlog items or only the tasks assigned to team members fails to address the selection of items geared towards the current Sprint's objectives. Thus, the combination of selected items and a plan for delivery is what defines the Sprint Backlog.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy