Is it true that the Development Team can change its Sprint Backlog during a Sprint?

Prepare for the Professional Scrum Master I Test. Tackle multiple choice questions with hints and explanations. Get ready to ace your exam!

The statement is true; the Development Team can indeed change its Sprint Backlog during a Sprint. This flexibility is a key aspect of Scrum. The Sprint Backlog is a living artifact composed of items from the Product Backlog that the Development Team has chosen to work on during the current Sprint. As the team progresses, they may find a need to adapt their plan based on new insights, challenges encountered, or changes in priorities.

This adaptability allows the team to respond to changes effectively, ensuring they can deliver the highest value possible by the end of the Sprint. Changes can involve any adjustments, such as adding new tasks, re-prioritizing items, or removing tasks that are no longer relevant, as long as they align with the Sprint Goal.

This understanding underscores the collaborative and self-organizing nature of the Development Team in Scrum, emphasizing their autonomy in managing their work while still maintaining focus on delivering the Sprint Goal.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy