Can the Definition of Done be adjusted during a Sprint Retrospective?

Prepare for the Professional Scrum Master I Test. Tackle multiple choice questions with hints and explanations. Get ready to ace your exam!

The Definition of Done can indeed be reviewed and adapted during a Sprint Retrospective, making this choice the correct one. During the retrospective, the Scrum Team evaluates their processes, practices, and outcomes, which includes discussing the Definition of Done. This is a critical aspect because the Definition of Done should reflect the current understanding and quality standards the team aims to achieve. If the team identifies areas for improvement or changes in the product requirements, they can propose modifications to the Definition of Done to ensure it aligns with their evolving work context.

Adjusting the Definition of Done during the Sprint Retrospective allows the team to foster continuous improvement, a core principle of Scrum. By doing so, they enhance their ability to deliver value consistently, incorporating lessons learned from the current Sprint.

The other choices present various misconceptions about the Definition of Done and its flexibility. It is not fixed and can be adjusted as needed, even within a Sprint Retrospective. Such changes can be made collaboratively by the entire Scrum Team, not just the Product Owner. The idea that changes can only occur after the Sprint ends misinterprets the Scrum framework's emphasis on continuous improvement throughout the entire Scrum process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy